Dr. Cone’s Perspective December 5, 2018

I want to make sure that we remain transparent throughout our bond project. We have met with our architects, Gara/Bomberger & Associates, to discuss next steps and general timelines and I would like to share some of that information.

 

January 2019

 

  • Site Survey

 

February 2019

 

  • Begin the design process

 

March 2019

 

  • Approve design

 

July 2019

 

  • Project “Bid” as a Competitive Sealed Proposal

 

August/September 2019

 

  • Award Contract for Construction

 

December 2020

 

  • Construction Complete

 

We hope the construction will only take approximately 16 months. Additional information will be shared throughout all phases of the project.